DIGGIN' DOWNTOWN UPDATE - 1/3


Date: January 3, 2025

Recent Weeks:

·         General site set up and safety fence installation

·         Pavement removal

·         Existing utility investigation

Next Week:

Phase 1A Washington Street

·         No work scheduled for next week due to low temperatures.

Looking Ahead:

·         Water main construction will continue through the following weeks.

Follow along here to see the latest progress!