DIGGIN DOWNTOWN UPDATE - 12/19


Date: December 19, 2025

Recent Weeks:
Underground Utility Service Installation (Jefferson St)
Sidewalk Installation (Main St/East Jefferson St)
Main Street & East Jefferson is Now Open

Next Week: Phase 2A Jefferson Street.
Monday 12/22 to Wednesday 12/24– Contractor to continue sanitary sewer installation and begin sidewalk installation west of Main/Jefferson intersection.
Thursday 12/25 – No work anticipated on site.
Friday 12/26 – Contractor may be on site to continue sidewalk installation.

Looking Ahead:
West Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation. All of Fillmore Street is anticipated to close in January (weather dependent).