DIGGIN DOWNTOWN UPDATE - 12/19
Date: December 19, 2025
Recent Weeks:
Underground Utility Service Installation
(Jefferson St)
Sidewalk Installation (Main St/East Jefferson St)
Main Street & East Jefferson is Now Open
Next Week:
Phase 2A Jefferson Street.
Monday 12/22 to Wednesday 12/24– Contractor to continue sanitary sewer installation and
begin sidewalk installation west of Main/Jefferson intersection.
Thursday 12/25 – No work anticipated on site.
Friday 12/26 – Contractor may be on site to continue sidewalk installation.
Looking Ahead:
West Jefferson Street between Main Street and Fillmore Street will remain closed for utility
installation. All of Fillmore Street is anticipated to close in January (weather dependent).
Osceola Chamber Main Street
115 E Washington St, PO Box 425
Osceola, IA 50213
641-342-4200
www.osceolachamber.com