DIGGIN' DOWNTOWN UPDATE - 3-28


Date: March 28, 2025

Recent Weeks:

-Sanitary sewer service installation

-Water main installation and water main services completed on Washington Street.

Next Week:

Phase 1A Washington Street

-Monday 3/31 to Wednesday 4/2 – Contractor will finish sanitary sewer service installations as well as replace existing sanitary sewer manholes along Washington Street.

-Thursday 4/3 to Friday 4/4 – Contractor will begin storm sewer installation along Washington Street.

-Sidewalk preparation may begin this week, contingent upon the completion of sanitary sewer installations.

Looking Ahead:

-Washington Street will remain closed as storm sewer installation continues through the following weeks.

- Main Street is expected to close within the next 3-4 weeks following the completion of the storm sewer installation.