DIGGIN' DOWNTOWN UPDATE - 7/11


Date: July 11, 2025

 

Recent Weeks:

Roadway Extended East to Intersection (Washington St)

Permeable Paver Installation (Washington St)

West Washington Intersection Opened (Washington Street)

Intakes Installed (Main Street)

Storm Sewer Installation (Washington Street/Main Street)


Next Week:

Phase 1A Washington Street

Monday 7/14 to Friday 7/18 – Contractor to continue permeable paver, subdrain, and curb and gutter installation along Washington Street.

Phase 1B Main Street

Monday 7/7 to Friday 7/11 – Storm sewer installation along East Washington


Looking Ahead:

Washington Street will remain closed as paving and permeable paver installations continue throughout the following weeks. Main Street and East Washington Street will remain closed for utility installation.