DIGGIN DOWNTOWN UPDATE - 1/30/26


Date: January 30, 2026

Recent Weeks:
Sanitary Sewer Installation (Jefferson St)

Next Week:
Phase 2A Jefferson Street.
Monday 2/2 to Friday 2/6 – Pending warmer weather, contractor to continue sanitary and storm sewer installation. Pavement preparation along Jefferson Street will follow the completion of utility installation.

Looking Ahead:
Jefferson Street between Main Street and Fillmore Street will remain closed for utility and roadway installation. Fillmore Street is expected to fully close in late February (weather dependent).