DIGGIN DOWNTOWN UPDATE - 2/20/26


Date: February 20, 2026

Recent Weeks:

Water Main Installation (Fillmore St)

Pavement Removal (Fillmore St)

Paving Preparation and Installation (Jefferson St)

Next Week:

Phase 2A Jefferson Street.

Monday 2/23 to Friday 2/27 – Contractor to continue roadway paving and will begin excavation for permeable paver installations.

Phase 2B Fillmore Street.

Monday 2/23 to Friday 2/27 – Contractor to continue existing pavement removal and will begin water service installation.

Looking Ahead:

Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.