DIGGIN DOWNTOWN UPDATE - 2/6/26


Date: February 6, 2026

Recent Weeks:

Sanitary Sewer Installation (Jefferson St)

Pavement Removal (Fillmore St)

Next Week:

Phase 2A Jefferson Street.

Monday 2/9 to Friday 2/13 – Contractor to continue roadway and sidewalk paving.

Phase 2B Fillmore Street.

Monday 2/9 to Friday 2/13 – Contractor to begin water main installation on the east side of Fillmore Street.

Looking Ahead:

Jefferson Street between Main Street and Fillmore Street will remain closed for roadway installation.  Fillmore Street is expected to fully close February 16 (weather dependent).

Originally posted by Osceola Chamber Main Street via Locable