DIGGIN DOWNTOWN UPDATE - 3/20


Date: March 20, 2026

Recent Weeks:

Storm Sewer Installation (Fillmore St)

Curb and Gutter Installation (Jefferson St)

Permeable Paver Installation (Jefferson St)

Sidewalk Installation (Jefferson St)

Next Week:

Phase 2A Jefferson Street.

Monday 3/23 to Friday 3/27

·         Install permeable pavers south side of Jefferson Street

·         Install pocket park aggregate and permeable paver system

·         Install remaining sections of PCC curb and gutter and sidewalk.

Phase 2B Fillmore Street.

Monday 3/16 to Friday 3/20 –Continue storm sewer installation.

Looking Ahead:

Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.