DIGGIN DOWNTOWN UPDATE - 3/30


Date: March 27, 2026

Recent Weeks:

Storm Sewer Installation (Fillmore St)

Curb and Gutter Installation (Jefferson St)

Permeable Paver Installation (Jefferson St)

Sidewalk Installation (Jefferson St)

Next Week:

Phase 2A Jefferson Street.

Monday 3/30 to Friday 4/3:

·         Install permeable pavers south side of Jefferson Street.

·         Install remaining sections of sidewalk.

·         Install streetlight bases.

Phase 2B Fillmore Street.

Monday 3/30 to Friday 4/3:

·         Continue storm sewer installation.

·         Begin removal of pavement in Fillmore Jefferson intersection.

Looking Ahead:

Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.