DIGGIN DOWNTOWN UPDATE - 3/30
Date: March 27, 2026
Recent Weeks:
Storm Sewer Installation (Fillmore St)
Curb and Gutter Installation (Jefferson St)
Permeable Paver Installation (Jefferson St)
Sidewalk Installation (Jefferson St)
Next Week:
Phase 2A Jefferson Street.
Monday 3/30 to Friday 4/3:
· Install permeable pavers south side of Jefferson Street.
· Install remaining sections of sidewalk.
· Install streetlight bases.
Phase 2B Fillmore Street.
Monday 3/30 to Friday 4/3:
· Continue storm sewer installation.
· Begin removal of pavement in Fillmore Jefferson intersection.
Looking Ahead:
Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.
Osceola Chamber Main Street
115 E Washington St, PO Box 425
Osceola, IA 50213
641-342-4200
www.osceolachamber.com