DIGGIN DOWNTOWN 3/6


Date: March 6, 2026

 

Recent Weeks:

Water Service Installation (Fillmore St)

Sanitary Sewer Service Installation (Fillmore St)

Paving Preparation and Installation (Jefferson St)

Permeable Paver Installation (Jefferson St)


Next Week:

Phase 2A Jefferson Street.

Monday 3/9 to Friday 3/13 – Curb and gutter, permeable paver aggregate, and sidewalk installation.

Phase 2B Fillmore Street.

Monday 3/9 to Friday 3/13 – Complete sanitary sewer service installation. Begin storm sewer installation


Looking Ahead:

Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.