Recent Weeks:

Storm Sewer/Water Main Installation (Fillmore St)

Sidewalk Installation (Fillmore St)


Next Week:

Phase 2B Fillmore Street.

Monday 4/20 to Friday 4/24:

·         Continue sidewalk installation.

·         Begin roadway pavement preparation.

·         Continue utility installation in Fillmore/Jefferson intersection.

 

Looking Ahead:

Fillmore Street and the west section of Jefferson Street will remain closed for roadway/utility installation.