DIGGIN DOWNTOWN UPDATE - 4/24


 Date: April 24, 2026

Recent Weeks:

Sanitary Sewer/Water Main Installation (Fillmore St)

Paving Preparation (Fillmore St)

Next Week:

Phase 2A Jefferson Street.

Monday 4/27 to Friday 5/1:

·         Install light poles

 

Phase 2B Fillmore Street.

Monday 4/27 to Friday 5/1:

·         Continue roadway paving

·         Continue utility installation in Fillmore/Jefferson intersection

·         Install electrical conduit

 

Looking Ahead:

Fillmore Street and the western section of Jefferson Street will remain closed for roadway/utility installation.

 