DIGGIN DOWNTOWN UPDATE - 4/3


Date: April 3, 2026

 

Recent Weeks:

Storm Sewer Installation (Fillmore St)

Pavement Removal (Fillmore St)

Permeable Paver Installation (Jefferson St)

Sidewalk Installation (Jefferson St)

Light Pole Installation (Jefferson St)

 

Next Week:

Phase 2A Jefferson Street.

Monday 4/6 to Friday 4/10:

·         Install remaining sections of sidewalk, ramps, bench pads.

·         Install permeable pavers.

·         Install streetlights.

 

Phase 2B Fillmore Street.

Monday 4/6 to Friday 4/10:

·         Continue storm sewer installation.

·         Begin utility installation in Fillmore/Jefferson intersection.

 

Looking Ahead:

Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.