DIGGIN DOWNTOWN UPDATE - 5/15


Date: May 15, 2026

 

Recent Weeks:

Permeable Paver Rock Installation (Fillmore St)

Subdrain Installation Paving (Fillmore St)

Curb and Gutter Installation (Fillmore St)

All storm, sewer and water utility work has been completed.


Next Week:

Phase 2B Fillmore Street.

Monday 5/18 to Friday 5/22:

Curb and gutter installation on west side.

Sidewalk installation on east side.

Light pole base installation.

Begin concrete preparation in Fillmore/Jefferson intersection.


Looking Ahead:

Fillmore Street and the western section of Jefferson Street will remain closed for roadway installation.