DIGGIN DOWNTOWN UPDATE - 6/12


Date: June 12, 2026


Recent Weeks:

Sidewalk Installation (Fillmore St)

Road Paving (Fillmore St)

Light Pole Installation (Fillmore St)

Seeding/Restoration (Fillmore St)

 

Next Week:

Phase 2B Fillmore Street.

Monday 6/15 to Friday 6/19:

·         Finish sidewalk installation at Fillmore/Jefferson intersection

·         Joint Sealing along Fillmore Street

·         Site Cleanup and Restoration

 

Looking Ahead:

Fillmore Street and the western section of Jefferson Street will remain closed for roadway installation.