DIGGIN DOWNTOWN UPDATE - 6/19


Date: June 19, 2026

Recent Weeks:

The square is now all open to traffic!

Sidewalk Installation (Fillmore St)

Light Pole Installation (Fillmore St)

Seeding/Restoration (Fillmore St)

Joint Filling & Pavement Striping (Fillmore St)

Next Week:

Phase 2B Fillmore Street.

Monday 6/22 to Friday 6/26:

·         Continue installation of permeable pavers in the Fillmore Street Alley

·         Continue site cleanup and restoration

Looking Ahead:

The alley at mid-block of Fillmore Street will remain closed for permeable paver installation. The Jefferson Street mid-block alley will begin after the Fillmore Street alley is completed.

Originally posted by Osceola Chamber Main Street via Locable